AI InterviewSearch…Search problems, topics, or pages…Ctrl KGet started
Easyrates

~45s

A and B working together

A can finish a job in 12 days and B in 18 days. Working together, how long do they take?

Show the answer and the worked solution

Correct answer: B.

7.2 days

Worked solution

  1. A does 1/12 per day, B does 1/18 per day.
  2. Together: 1/12 + 1/18 = 3/36 + 2/36 = 5/36 per day.
  3. Time = 36/5 = 7.2 days.

Answer: 7.2 days.

The idea

Work in rates, not times. Or take the total work as the LCM of the times (36 units): A does 3 a day, B does 2, together 5, so 36/5 days. The LCM method avoids fractions entirely.

Shortcut. For two workers, time together = product ÷ sum = 12 × 18 ÷ 30 = 216 ÷ 30 = 7.2 days.

Common trap. 7.5 days — averaging the times to 15 days and halving, as if both were 15-day workers; the faster worker counts for more, pulling the time below 7.5.

A and B working together — Time & Work Aptitude Question

A and B working together: A can finish a job in 12 days and B in 18 days. Working together, how long do they take? Answer and worked solution on CodeKairo.

Question

A can finish a job in 12 days and B in 18 days. Working together, how long do they take?

Options

  1. 6 days
  2. 7.2 days
  3. 7.5 days
  4. 8 days
Show the answer and the worked solution

Correct answer: B. 7.2 days

Worked solution

  1. A does 1/12 per day, B does 1/18 per day.
  2. Together: 1/12 + 1/18 = 3/36 + 2/36 = 5/36 per day.
  3. Time = 36/5 = 7.2 days.

Answer: 7.2 days.

The idea

Work in rates, not times. Or take the total work as the LCM of the times (36 units): A does 3 a day, B does 2, together 5, so 36/5 days. The LCM method avoids fractions entirely.

Shortcut. For two workers, time together = product ÷ sum = 12 × 18 ÷ 30 = 216 ÷ 30 = 7.2 days.

Common trap. 7.5 days — averaging the times to 15 days and halving, as if both were 15-day workers; the faster worker counts for more, pulling the time below 7.5.