Time & Work aptitude questions

Rates of work, pipes and cisterns, alternating days and efficiency.

0 of 44 solved in this view

Formula sheetTime & Work: the essentialsFormula sheetTime & Work: the essentialsShow

  • Work in rates, not times: a job done in a days is 1/a of the job per day. Rates add; times do not.
  • A in a days and B in b days, working together: ab/(a + b) days.
  • LCM method: take the total work as the LCM of the given times, so every rate is a whole number of units a day.
  • Efficiency is inversely proportional to time. Twice as efficient means half the time; x% more efficient means 100x/(100 + x) per cent less time.
  • Three pairs: adding the rates of A + B, B + C and C + A counts everyone twice, so halve the sum.
  • Chain rule: (M₁ × D₁ × H₁)/W₁ = (M₂ × D₂ × H₂)/W₂ for men, days, hours and work done. Convert a mixed gang of men and women into one unit first.
  • Pipes and cisterns: inlets add rate, outlets and leaks subtract it. A pipe that fills in a hours but takes b hours with a leak means the leak alone empties it in ab/(b − a) hours.
  • Alternate days: find the work per cycle, count the whole cycles, then finish the remainder day by day, in order.
  • When someone leaves early, write one equation in the total time; the leaver works fewer days.

Example: A takes 24 days and B 40. Take the job as 120 units: A does 5 a day and B 3, so together they need 120/8 = 15 days.

Questions44

1

A and B working together

A can finish a job in 12 days and B in 18 days. Working together, how long do they take?

rates

45s

Easy
2

A leaves after four days

A and B can finish a job in 10 and 15 days respectively. They start together, but A leaves after 4 days. How many more days does B need to finish?

leaving early

60s

Medium
3

Two inlets and one outlet

Pipe A fills a tank in 6 hours, pipe B in 9 hours, and pipe C empties a full tank in 18 hours. With all three open, how long does the tank take to fill?

pipes

60s

Medium
4

A is twice as efficient as B

A is twice as efficient as B, and together they finish a job in 8 days. How long would B alone take?

efficiency

45s

Medium
5

Men, women and one job

6 men or 10 women can complete a job in 15 days. How many days will 3 men and 5 women take together?

equivalence

60s

Medium
6

Working on alternate days

A can do a job in 10 days and B in 15 days. They work on alternate days, A starting first. In how many days is the job finished?

alternate days

90s

Hard
7

A in 10 days, B in 15

A can finish a job in 10 days and B in 15 days. Working together, how long do they take?

rates

45s

Easy
8

A in 6 days, B in 10

A can do a piece of work in 6 days and B in 10 days. How long will they take together?

rates

45s

Easy
9

Finding B's time alone

A and B together can complete a work in 8 days. A alone takes 12 days. How long would B alone take?

rates

45s

Easy
10

Twice as fast

A works twice as fast as B. Together they finish a job in 12 days. How long would B alone take?

efficiency

60s

Medium
11

Three times as good, sixty days sooner

A is three times as good a workman as B and takes 60 days less than B to finish a job. How long do they take working together?

efficiency

105s

Hard
12

Twenty-five percent more efficient

A is 25% more efficient than B and takes 10 days less to finish a job. How many days does A take?

efficiency

105s

Hard
13

Finding C's time

A, B and C together finish a work in 4 days. A alone takes 12 days and B alone 18 days. How long would C alone take?

rates

75s

Medium
14

Three pairs of workers

A and B together can do a work in 12 days, B and C in 15 days, and C and A in 20 days. How long will all three together take?

rates

105s

Hard
15

A alone, from the pairs

A and B together take 12 days, B and C take 15 days, and all three together take 10 days. How long would A alone take?

rates

60s

Medium
16

A starts, B finishes

A can do a work in 15 days. He works for 5 days and then B finishes the rest in 12 days. How long would B alone take for the whole work?

partial work

75s

Medium
17

Together, then B alone

A can do a work in 12 days and B in 15 days. They work together for 4 days, after which A leaves. In how many more days will B finish?

partial work

90s

Medium
18

B leaves partway

A and B together can do a work in 30 days. They work together for 20 days, then B leaves and A finishes the rest in 20 more days.

partial work

75s

Medium
19

A leaves five days before the end

A can do a work in 20 days and B in 30 days. They begin together, but A leaves 5 days before the work is finished. In how many days is the work completed?

partial work

120s

Hard
20

Alternate days: 20 and 30 days

A can complete a work in 20 days and B in 30 days. They work on alternate days, with A starting. In how many days is the work finished?

alternate days

105s

Hard
21

Two taps used alternately

Tap A fills a tank in 4 hours and tap B in 6 hours. They are opened alternately for one hour each, starting with A. How long does the tank take to fill?

alternate days · pipes

135s

Hard
22

Two inlets and an outlet

Pipe A fills a tank in 12 hours, pipe B in 15 hours, and pipe C empties a full tank in 20 hours. With all three open, how long does the tank take to fill?

pipes

60s

Medium
23

A leak in the tank

A tap fills a tank in 6 hours. A leak at the bottom empties a full tank in 12 hours. With both working, how long does the tank take to fill?

pipes

45s

Easy
24

The leak costs an hour

A pipe fills a cistern in 4 hours, but because of a leak it takes 1 hour longer. How long would the leak alone take to empty a full cistern?

pipes

75s

Medium
25

From nine hours to ten

A cistern is normally filled in 9 hours, but a leak makes it take 10 hours. How long would the leak alone take to empty the full cistern?

pipes

60s

Medium
26

Closing one tap early

Two pipes fill a tank in 20 minutes and 30 minutes respectively.

pipes

105s

Hard
27

One pipe finishes the job

Two pipes can fill a tank in 10 minutes and 15 minutes. Both are opened for 4 minutes, then the first is closed.

pipes

90s

Medium
28

Capacity from a waste pipe

Two taps fill a cistern in 30 and 40 minutes. A waste pipe empties 3 gallons per minute. With all three open the cistern fills in 60 minutes.

pipes

135s

Hard
29

Men and women together

3 men or 6 women can complete a work in 20 days. How long will 4 men and 4 women take?

equivalence

90s

Medium
30

Women and children

10 women can complete a work in 7 days and 10 children take 14 days. How long will 5 women and 10 children take together?

equivalence

90s

Medium
31

More men to finish in 6 days instead of 8

12 men can complete a work in 8 days. How many men are needed to finish it in 6 days?

man-days

45s

Easy
32

More men join partway

12 men undertake a work expected to take 20 days. After 8 days, 4 more men join. In how many days in total is the work finished?

man-days

105s

Hard
33

Some men leave

24 men can complete a work in 16 days. After 4 days, 8 men leave. How many more days will the rest take to finish?

man-days

90s

Medium
34

A contractor falls behind

A contractor undertakes to finish a job in 40 days with 100 men. After 30 days only two-thirds of the work is done.

man-days

135s

Hard
35

Hectares reaped

If 8 men can reap 80 hectares in 24 days, how many hectares can 36 men reap in 30 days?

man-days

90s

Medium
36

Length of wall built

If 20 men can build a wall 56 metres long in 6 days, what length can 35 men build in 3 days?

man-days

90s

Medium
37

Working different hours a day

39 people can repair a road in 12 days working 5 hours a day. In how many days will 30 people working 6 hours a day complete it?

man-days

90s

Medium
38

Men, women and hours

15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men?

equivalence · man-days

150s

Hard
39

Half the work, a third of the work

A does half a job in 5 days; B does one-third of the same job in 5 days. How long will they take together to complete it?

partial work

90s

Medium
40

Four-fifths done in twenty days

A completes four-fifths of a work in 20 days. How many more days will he take to finish the rest?

partial work

45s

Easy
41

Sharing the payment

A can do a work in 6 days and B in 8 days. With C's help they finish it in 3 days and are paid ₹600 in all. What is C's share?

wages

135s

Hard
42

C's help finishes it in four days

A alone takes 8 days and B alone 12 days. With C's help they finish the work in 4 days. How long would C alone take?

rates

75s

Medium
43

Capacity from a tap and a leak

A leak can empty a full tank in 8 hours. With a tap admitting 6 litres per minute also open, the full tank empties in 12 hours.

pipes

150s

Hard
44

How long B alone would take

A and B can do a work in 10 days, B and C in 15 days, and A and C in 12 days. How long would B alone take?

rates

120s

Hard

Showing 44 of 44

Time & Work Aptitude Questions with Solutions

44 Time & Work questions with hints, worked solutions and time targets — 7 easy · 22 medium · 15 hard.

  • Section: Quantitative Aptitude
  • Questions: 44
  • By difficulty: 7 easy · 22 medium · 15 hard
  • Cost: Free, unlimited on every plan

Rates of work, pipes and cisterns, alternating days and efficiency.

Time & Work: the essentials

  • Work in rates, not times: a job done in a days is 1/a of the job per day. Rates add; times do not.
  • A in a days and B in b days, working together: ab/(a + b) days.
  • LCM method: take the total work as the LCM of the given times, so every rate is a whole number of units a day.
  • Efficiency is inversely proportional to time. Twice as efficient means half the time; x% more efficient means 100x/(100 + x) per cent less time.
  • Three pairs: adding the rates of A + B, B + C and C + A counts everyone twice, so halve the sum.
  • Chain rule: (M₁ × D₁ × H₁)/W₁ = (M₂ × D₂ × H₂)/W₂ for men, days, hours and work done. Convert a mixed gang of men and women into one unit first.
  • Pipes and cisterns: inlets add rate, outlets and leaks subtract it. A pipe that fills in a hours but takes b hours with a leak means the leak alone empties it in ab/(b − a) hours.
  • Alternate days: find the work per cycle, count the whole cycles, then finish the remainder day by day, in order.
  • When someone leaves early, write one equation in the total time; the leaver works fewer days.

Example: A takes 24 days and B 40. Take the job as 120 units: A does 5 a day and B 3, so together they need 120/8 = 15 days.

Questions

  1. A and B working together Easy
    A can finish a job in 12 days and B in 18 days. Working together, how long do they take?
  2. A leaves after four days Medium
    A and B can finish a job in 10 and 15 days respectively. They start together, but A leaves after 4 days. How many more days does B need to finish?
  3. Two inlets and one outlet Medium
    Pipe A fills a tank in 6 hours, pipe B in 9 hours, and pipe C empties a full tank in 18 hours. With all three open, how long does the tank take to fill?
  4. A is twice as efficient as B Medium
    A is twice as efficient as B, and together they finish a job in 8 days. How long would B alone take?
  5. Men, women and one job Medium
    6 men or 10 women can complete a job in 15 days. How many days will 3 men and 5 women take together?
  6. Working on alternate days Hard
    A can do a job in 10 days and B in 15 days. They work on alternate days, A starting first. In how many days is the job finished?
  7. A in 10 days, B in 15 Easy
    A can finish a job in 10 days and B in 15 days. Working together, how long do they take?
  8. A in 6 days, B in 10 Easy
    A can do a piece of work in 6 days and B in 10 days. How long will they take together?
  9. Finding B's time alone Easy
    A and B together can complete a work in 8 days. A alone takes 12 days. How long would B alone take?
  10. Twice as fast Medium
    A works twice as fast as B. Together they finish a job in 12 days. How long would B alone take?
  11. Three times as good, sixty days sooner Hard
    A is three times as good a workman as B and takes 60 days less than B to finish a job. How long do they take working together?
  12. Twenty-five percent more efficient Hard
    A is 25% more efficient than B and takes 10 days less to finish a job. How many days does A take?
  13. Finding C's time Medium
    A, B and C together finish a work in 4 days. A alone takes 12 days and B alone 18 days. How long would C alone take?
  14. Three pairs of workers Hard
    A and B together can do a work in 12 days, B and C in 15 days, and C and A in 20 days. How long will all three together take?
  15. A alone, from the pairs Medium
    A and B together take 12 days, B and C take 15 days, and all three together take 10 days. How long would A alone take?
  16. A starts, B finishes Medium
    A can do a work in 15 days. He works for 5 days and then B finishes the rest in 12 days. How long would B alone take for the whole work?
  17. Together, then B alone Medium
    A can do a work in 12 days and B in 15 days. They work together for 4 days, after which A leaves. In how many more days will B finish?
  18. B leaves partway Medium
    A and B together can do a work in 30 days. They work together for 20 days, then B leaves and A finishes the rest in 20 more days.
  19. A leaves five days before the end Hard
    A can do a work in 20 days and B in 30 days. They begin together, but A leaves 5 days before the work is finished. In how many days is the work completed?
  20. Alternate days: 20 and 30 days Hard
    A can complete a work in 20 days and B in 30 days. They work on alternate days, with A starting. In how many days is the work finished?
  21. Two taps used alternately Hard
    Tap A fills a tank in 4 hours and tap B in 6 hours. They are opened alternately for one hour each, starting with A. How long does the tank take to fill?
  22. Two inlets and an outlet Medium
    Pipe A fills a tank in 12 hours, pipe B in 15 hours, and pipe C empties a full tank in 20 hours. With all three open, how long does the tank take to fill?
  23. A leak in the tank Easy
    A tap fills a tank in 6 hours. A leak at the bottom empties a full tank in 12 hours. With both working, how long does the tank take to fill?
  24. The leak costs an hour Medium
    A pipe fills a cistern in 4 hours, but because of a leak it takes 1 hour longer. How long would the leak alone take to empty a full cistern?
  25. From nine hours to ten Medium
    A cistern is normally filled in 9 hours, but a leak makes it take 10 hours. How long would the leak alone take to empty the full cistern?
  26. Closing one tap early Hard
    Two pipes fill a tank in 20 minutes and 30 minutes respectively.
  27. One pipe finishes the job Medium
    Two pipes can fill a tank in 10 minutes and 15 minutes. Both are opened for 4 minutes, then the first is closed.
  28. Capacity from a waste pipe Hard
    Two taps fill a cistern in 30 and 40 minutes. A waste pipe empties 3 gallons per minute. With all three open the cistern fills in 60 minutes.
  29. Men and women together Medium
    3 men or 6 women can complete a work in 20 days. How long will 4 men and 4 women take?
  30. Women and children Medium
    10 women can complete a work in 7 days and 10 children take 14 days. How long will 5 women and 10 children take together?
  31. More men to finish in 6 days instead of 8 Easy
    12 men can complete a work in 8 days. How many men are needed to finish it in 6 days?
  32. More men join partway Hard
    12 men undertake a work expected to take 20 days. After 8 days, 4 more men join. In how many days in total is the work finished?
  33. Some men leave Medium
    24 men can complete a work in 16 days. After 4 days, 8 men leave. How many more days will the rest take to finish?
  34. A contractor falls behind Hard
    A contractor undertakes to finish a job in 40 days with 100 men. After 30 days only two-thirds of the work is done.
  35. Hectares reaped Medium
    If 8 men can reap 80 hectares in 24 days, how many hectares can 36 men reap in 30 days?
  36. Length of wall built Medium
    If 20 men can build a wall 56 metres long in 6 days, what length can 35 men build in 3 days?
  37. Working different hours a day Medium
    39 people can repair a road in 12 days working 5 hours a day. In how many days will 30 people working 6 hours a day complete it?
  38. Men, women and hours Hard
    15 men take 21 days of 8 hours each to do a piece of work. How many days of 6 hours each would 21 women take, if 3 women do as much work as 2 men?
  39. Half the work, a third of the work Medium
    A does half a job in 5 days; B does one-third of the same job in 5 days. How long will they take together to complete it?
  40. Four-fifths done in twenty days Easy
    A completes four-fifths of a work in 20 days. How many more days will he take to finish the rest?
  41. Sharing the payment Hard
    A can do a work in 6 days and B in 8 days. With C's help they finish it in 3 days and are paid ₹600 in all. What is C's share?
  42. C's help finishes it in four days Medium
    A alone takes 8 days and B alone 12 days. With C's help they finish the work in 4 days. How long would C alone take?
  43. Capacity from a tap and a leak Hard
    A leak can empty a full tank in 8 hours. With a tap admitting 6 litres per minute also open, the full tank empties in 12 hours.
  44. How long B alone would take Hard
    A and B can do a work in 10 days, B and C in 15 days, and A and C in 12 days. How long would B alone take?