Some men leave

24 men can complete a work in 16 days. After 4 days, 8 men leave. How many more days will the rest take to finish?

Show the answer and the worked solution

Correct answer: C.

18 days

Worked solution

  1. Total work = 384 man-days.
  2. In 4 days: 24 × 4 = 96 done, leaving 288.
  3. With 16 men: 288 ÷ 16 = 18 more days.

Answer: 18 days.

The idea

Man-days again. Note the question asks for the additional days, not the total elapsed time.

Shortcut. What is left is 12 days' work for 24 men; 16 men need 12 × 24/16 = 18 days.

Common trap. 16 days — adding a third to the remaining 12 days because a third of the men left; two thirds of the crew need 3/2 of the time, 18 days.

Some men leave — Time & Work Aptitude Question

Some men leave: 24 men can complete a work in 16 days. After 4 days, 8 men leave. Answer and worked solution on CodeKairo.

Question

24 men can complete a work in 16 days. After 4 days, 8 men leave. How many more days will the rest take to finish?

Options

  1. 14 days
  2. 16 days
  3. 18 days
  4. 20 days
Show the answer and the worked solution

Correct answer: C. 18 days

Worked solution

  1. Total work = 384 man-days.
  2. In 4 days: 24 × 4 = 96 done, leaving 288.
  3. With 16 men: 288 ÷ 16 = 18 more days.

Answer: 18 days.

The idea

Man-days again. Note the question asks for the additional days, not the total elapsed time.

Shortcut. What is left is 12 days' work for 24 men; 16 men need 12 × 24/16 = 18 days.

Common trap. 16 days — adding a third to the remaining 12 days because a third of the men left; two thirds of the crew need 3/2 of the time, 18 days.