Easyman-days

~45s

More men to finish in 6 days instead of 8

12 men can complete a work in 8 days. How many men are needed to finish it in 6 days?

Show the answer and the worked solution

Correct answer: C.

16

Worked solution

  1. Work = 12 × 8 = 96 man-days.
  2. Men needed = 96 ÷ 6 = 16.

Answer: 16.

The idea

Keep the man-days product constant. The count of workers rises exactly as the time falls.

Shortcut. Time falls to 6/8 = 3/4, so the crew rises by 4/3: 12 × 4/3 = 16 men.

Common trap. 14 — adding the 2 days saved to the 12 men, a direct adjustment where an inverse one is needed.

More men to finish in 6 days instead of 8 — Aptitude

More men to finish in 6 days instead of 8: 12 men can complete a work in 8 days. How many men are needed to finish… Answer and worked solution on CodeKairo.

Question

12 men can complete a work in 8 days. How many men are needed to finish it in 6 days?

Options

  1. 14
  2. 15
  3. 16
  4. 18
Show the answer and the worked solution

Correct answer: C. 16

Worked solution

  1. Work = 12 × 8 = 96 man-days.
  2. Men needed = 96 ÷ 6 = 16.

Answer: 16.

The idea

Keep the man-days product constant. The count of workers rises exactly as the time falls.

Shortcut. Time falls to 6/8 = 3/4, so the crew rises by 4/3: 12 × 4/3 = 16 men.

Common trap. 14 — adding the 2 days saved to the 12 men, a direct adjustment where an inverse one is needed.