Hardman-days

~105s

More men join partway

12 men undertake a work expected to take 20 days. After 8 days, 4 more men join. In how many days in total is the work finished?

Show the answer and the worked solution

Correct answer: B.

17 days

Worked solution

  1. Total work = 240 man-days.
  2. In 8 days: 12 × 8 = 96 done, leaving 144.
  3. With 16 men: 144 ÷ 16 = 9 more days.
  4. Total = 8 + 9 = 17 days.

Answer: 17 days.

The idea

Track man-days used and remaining. The answer is the total elapsed time, so remember to add the first stretch back on.

Shortcut. The last 12 days' work for 12 men takes 16 men 12 × 12/16 = 9 days, so the total is 8 + 9 = 17.

Common trap. 16 days — cutting the remaining 12 days by a third because the crew grew by a third; a third more men cuts time by a quarter, to 9 days.

More men join partway — Time & Work Aptitude Question

More men join partway: 12 men undertake a work expected to take 20 days. After 8 days, 4 more men join. Answer and worked solution on CodeKairo.

Question

12 men undertake a work expected to take 20 days. After 8 days, 4 more men join. In how many days in total is the work finished?

Options

  1. 16 days
  2. 17 days
  3. 18 days
  4. 19 days
Show the answer and the worked solution

Correct answer: B. 17 days

Worked solution

  1. Total work = 240 man-days.
  2. In 8 days: 12 × 8 = 96 done, leaving 144.
  3. With 16 men: 144 ÷ 16 = 9 more days.
  4. Total = 8 + 9 = 17 days.

Answer: 17 days.

The idea

Track man-days used and remaining. The answer is the total elapsed time, so remember to add the first stretch back on.

Shortcut. The last 12 days' work for 12 men takes 16 men 12 × 12/16 = 9 days, so the total is 8 + 9 = 17.

Common trap. 16 days — cutting the remaining 12 days by a third because the crew grew by a third; a third more men cuts time by a quarter, to 9 days.