AI InterviewSearch…Search problems, topics, or pages…Ctrl KGet started
Mediumman-days

~90s

Length of wall built

If 20 men can build a wall 56 metres long in 6 days, what length can 35 men build in 3 days?

Show the answer and the worked solution

Correct answer: B.

49 m

Worked solution

  1. 20 × 6 = 120 man-days give 56 m.
  2. 35 × 3 = 105 man-days.
  3. Length = 56 × 105/120 = 49 m.

Answer: 49 m.

The idea

Set up the proportion output ∝ man-days. More men but fewer days here nets out to slightly less work, so the answer must be under 56.

Shortcut. Man-days go from 120 to 105, a ratio of 7/8, so the wall is 56 × 7/8 = 49 m.

Common trap. 56 m — assuming 35 men for half the days cancels out; 35 is 1.75 times 20, not twice, so output falls to 7/8 of 56.

Length of wall built — Time & Work Aptitude Question

Length of wall built: If 20 men can build a wall 56 metres long in 6 days, what length can 35 men build in 3 days? Answer and worked solution on CodeKairo.

Question

If 20 men can build a wall 56 metres long in 6 days, what length can 35 men build in 3 days?

Options

  1. 42 m
  2. 49 m
  3. 56 m
  4. 63 m
Show the answer and the worked solution

Correct answer: B. 49 m

Worked solution

  1. 20 × 6 = 120 man-days give 56 m.
  2. 35 × 3 = 105 man-days.
  3. Length = 56 × 105/120 = 49 m.

Answer: 49 m.

The idea

Set up the proportion output ∝ man-days. More men but fewer days here nets out to slightly less work, so the answer must be under 56.

Shortcut. Man-days go from 120 to 105, a ratio of 7/8, so the wall is 56 × 7/8 = 49 m.

Common trap. 56 m — assuming 35 men for half the days cancels out; 35 is 1.75 times 20, not twice, so output falls to 7/8 of 56.