Half the work, a third of the work

A does half a job in 5 days; B does one-third of the same job in 5 days. How long will they take together to complete it?

Show the answer and the worked solution

Correct answer: B.

6 days

Worked solution

  1. A does 1/2 in 5 days, so the whole job would take 10 days.
  2. B does 1/3 in 5 days, so the whole job would take 15 days.
  3. Together: 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6.
  4. Time = 6 days.

Answer: 6 days.

The idea

Scale each partial job up to a whole-job time first, then add the rates. Adding the two partial times directly is meaningless.

Shortcut. In 5 days together they finish 1/2 + 1/3 = 5/6 of the job, so the whole takes 5 × 6/5 = 6 days.

Common trap. 5 days — treating a half plus a third as the whole job; 1/2 + 1/3 = 5/6 leaves a sixth undone.

Half the work, a third of the work — Aptitude Question

Half the work, a third of the work: A does half a job in 5 days; B does one-third of the same job in 5 days. Answer and worked solution on CodeKairo.

Question

A does half a job in 5 days; B does one-third of the same job in 5 days. How long will they take together to complete it?

Options

  1. 5 days
  2. 6 days
  3. 7.5 days
  4. 9 days
Show the answer and the worked solution

Correct answer: B. 6 days

Worked solution

  1. A does 1/2 in 5 days, so the whole job would take 10 days.
  2. B does 1/3 in 5 days, so the whole job would take 15 days.
  3. Together: 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6.
  4. Time = 6 days.

Answer: 6 days.

The idea

Scale each partial job up to a whole-job time first, then add the rates. Adding the two partial times directly is meaningless.

Shortcut. In 5 days together they finish 1/2 + 1/3 = 5/6 of the job, so the whole takes 5 × 6/5 = 6 days.

Common trap. 5 days — treating a half plus a third as the whole job; 1/2 + 1/3 = 5/6 leaves a sixth undone.