A starts, B finishes

A can do a work in 15 days. He works for 5 days and then B finishes the rest in 12 days. How long would B alone take for the whole work?

Show the answer and the worked solution

Correct answer: B.

18 days

Worked solution

  1. A does 5/15 = 1/3 of the work.
  2. B does the remaining 2/3 in 12 days.
  3. So B alone would take 12 × 3/2 = 18 days.

Answer: 18 days.

The idea

Find the fraction each person completes, then scale the partial time up to the whole. Never add the two given day counts.

Shortcut. A would have needed 10 more days for the rest; B needed 12, so B is 1.2 times as slow: 1.2 × 15 = 18 days.

Common trap. 24 days — doubling B's 12 days as if A had done half the job; A did only a third.

A starts, B finishes — Time & Work Aptitude Question

A starts, B finishes: A can do a work in 15 days. He works for 5 days and then B finishes the rest in 12 days. Answer and worked solution on CodeKairo.

Question

A can do a work in 15 days. He works for 5 days and then B finishes the rest in 12 days. How long would B alone take for the whole work?

Options

  1. 15 days
  2. 18 days
  3. 20 days
  4. 24 days
Show the answer and the worked solution

Correct answer: B. 18 days

Worked solution

  1. A does 5/15 = 1/3 of the work.
  2. B does the remaining 2/3 in 12 days.
  3. So B alone would take 12 × 3/2 = 18 days.

Answer: 18 days.

The idea

Find the fraction each person completes, then scale the partial time up to the whole. Never add the two given day counts.

Shortcut. A would have needed 10 more days for the rest; B needed 12, so B is 1.2 times as slow: 1.2 × 15 = 18 days.

Common trap. 24 days — doubling B's 12 days as if A had done half the job; A did only a third.